BPM generator dispatch:

Craig 1 will be retired in 27, however it is left on in order to preserve transmission rights

Craig 1,2 and 3 have a PMAX of 440. 470 MW accounts for 30 MW of station service.

Craig 3 should be dispatched at 440 - 145 = 295 in order to reflect the transfer of transmission
rights to Axial Basin

Axial Basin and Delores both have Transmission Network Service and are output at full.

Garnet Mesa is a previously studied NRIS project that should dispatched at 100% 

TOT2A dispatch changes:
In order to reach a TOT2A of 500 MW incrase the hydro by Montrose 
BMESA1-2, BMESA1-2, CRYSTAL, MORRO1-2 (1), MORRO1-2 (2)

Offset generation in FC area
Decrease FC_SOL, FCNGN4CC, FCNG4CC to offset